Our estimates for the 20 largest US data center campuses due to start coming online by late 2028: where they sit after the midterms and how many gigawatts the results put at risk.
Almost half the planned capacity sits in Texas, Ohio and Georgia, which elected governors who campaigned on pausing data centers. Most of it is later phases, so we put about 10 to 15 GW at real risk of delay.
For provider-by-provider scores see Midterms 2026.
Each bubble is a campus, sized by planned GW. Hover for a summary; click or press Enter for local votes, lawsuits and the governor.
GW is the announced full build, not what can be online in 24 months. Risk ratings are our judgment.
The pause pledges target new approvals, so campuses already being built are less exposed than their size suggests.