SpaceX's planned chip fab in Texas. What it has said, what the S-1 says about cost, and what is still only reported.
On the Q3 call SpaceX said a test chip should work around May or June 2027 in Austin.
The same call put volume production at Gibbons Creek in Q3 2028. A target, not capacity that exists.
The S-1 puts phase 1 at $55B, scaling to $119B, and calls the full figure a framework rather than a commitment.
Confirmed means SpaceX said it on a call or in a filing, as relayed by coverage. Source: BigGo, Oct 20, 2026.
A June video summary described a small Tesla AI5 pilot batch in 2026 and volume in 2027. The Q3 call dates are later, and the two may not describe the same stage. Source: video summary
SemiAnalysis counts a possible data center at Terafab in Texas with medium-high confidence. SpaceX has not described one. Source: Remio summary
Reported means it comes from outlets, analysts or creators without a company statement. Ground compute sites: Data center.