SpaceX’s proposed 6 GW AI campus beside the Apache power plant: what it would take, who has to approve it and our odds for each step.

The short answer

SpaceX said on Nov 4 that it is behind the application, which was filed under the name Tombstone Resources LLC. The outline holds up: up to nine buildings, about 6 GW at full build-out and 747 acres next to the Apache power plant. The county’s application also lists most of the bigger numbers going around: a 1.5 GW first phase, construction power targeted for March 2027, about $3.6B of grid upgrades and a 24 GWh battery. What it does not show is a signed power supply. We think Phase 1 is plausible but mostly 2028 capacity, and the full 6 GW is an option, not a plan. Power supply is the harder gate. The county vote comes first: we put about 35% on approval at the Dec 9 hearing and about 60% on county approval by the end of Q1 2027.

For the national picture see Midterms 2026. For SpaceX’s 13 GW plan see The Road to More GW. Each figure in the plan is checked on Cochise claims.

How big is 6 GW

The campus would be six times the Project Blue site Tucson turned away and twice La Osa, which Pinal County rejected in August. It would also be more than SpaceX’s whole compute fleet today.

Hatched is a claim we could not confirm. GW of power demand, not GPUs.

Who has to say yes

Seven steps stand between the filing and first power. Only the first is done.

    Political risk: our odds

    The county vote is the highest risk. The state regulator is mostly a question of timing, and a statewide ban looks unlikely.

    Approvals

    Our judgment, not a forecast.

    The build

    Our estimates, not company guidance and not advice. Energized means the first grid connection is live.

    The Arizona Corporation Commission is all Republican today and stays Republican after the Nov 3 vote. Both candidates for governor said before the vote that they oppose a statewide moratorium and want state water and power standards. Governor and commission results from Nov 3 are not reflected here.

    What the county is saying

    Public pressure is loud and the Board looks friendlier than the crowd.

    Arizona’s track record

    Big projects have been turned away or tightened in Arizona this year, but a rejection by one body has not always ended a project.

      What would move it

      These odds are judgment calls, not a forecast from SpaceX and not investment advice. The Cochise filing is public, but SpaceX has not published most of the project’s figures.